Netherlands offshore wind

Project pipeline & buildout trajectory · 21 GW by 2035 → 35 GW by 2040 · Birdview Energy estimate
0.0GW installed and operational
DATAKGG Letters to Parliament (May 2026) · RVO · windopzee.nl · OffshoreWIND.biz
TARGET35 GW by 2040 realistic · 40 GW government ambition
METHODRVO data · Birdview commissioning estimates
Data as of May 2026
MARKET BRIEFING · Q2 2026
The Dutch offshore
pipeline to 2040
0 GWoperational, awarded and tendered pipeline
0 GW2035 near-term goal
30 to 40 GW2040 range (revised Jul '25)

In July 2025 the government replaced the 50 GW 2040 target with a range of 30 to 40 GW; the 2026 coalition agreement aims for the top of that range. Birdview Energy works with 35 GW in 2040 as the realistic figure and a near-term 21 GW by 2035. The operational, awarded and tendered pipeline lands at roughly 23 GW. The areas designated in March 2026 and the new roadmap, due end of 2026, decide how much of the rest gets built.

01

North Sea project map

Click any marker for project details
STATUS
Operational
Construction
Planned
In tender

CAPACITY
< 250 MW
250 to 1000 MW
1000+ MW

GRID & AREAS
Landfall, straight-line indication
Grid connection point
Area 6/7, not in roadmap
Doordewind, revised shape
PROJECT DETAILS
Select a wind farm on the map
From Egmond aan Zee (2007) through the Hollandse Kust zones, the Netherlands has 4.7 GW operational across 11 wind farms. Everything after 2029 is multi-GW HVDC clusters further offshore.
  • Click any marker to see capacity, turbines and timeline
  • Toggle + Neighbours for BE / DE / GB / DK / FR / NO
  • Or pick a project from the register below
02

Buildout trajectory

2007 to 2040 · Netherlands only

Cumulative capacity vs annual additions

The total NL pipeline, including 4.7 GW already operational, reaches ~23 GW, a ~12 GW gap to the realistic 35 GW for 2040. The government ambition of 40 GW would leave a 17 GW gap; we consider it less realistic. Closing the gap needs area 6/7, designated in March 2026, which offers indicatively 11 GW in its first phase. Birdview Energy applies delays of 1 to 4 years on tender-stage projects and caps annual commissioning at about 2 GW, rising to 2.7 GW in the final year, to reflect supply-chain limits. Under those assumptions the 21 GW near-term goal lands in 2040. Hover or tap a bar for the project breakdown.
Cumulative (GW) Annual additions, stacked by project Realistic target (21 GW by 2035 → 35 GW by 2040)
Chart: Dutch offshore wind cumulative capacity reaches 4.7 GW operational in 2024 and about 23 GW by 2040, against a realistic target trajectory of 21 GW by 2035 and 35 GW by 2040. The project register below lists every project behind these figures.
REVISION · JULY 2025
The WIN plan replaced the 50 GW 2040 target with a range of 30 to 40 GW, citing higher costs and slower hydrogen demand. The 2026 coalition agreement aims for 40 GW; Birdview Energy uses 35 GW as the realistic figure.
NO-BID · OCT 2025
Nederwiek I-A tender received zero applications, a first for NL offshore wind. The 2026 subsidy tender moved to IJmuiden Ver Gamma-A and Gamma-B instead (2 × 1 GW on one TenneT platform, closing 10 December 2026). Nederwiek waits for the new roadmap, due end of 2026.
SPLIT · AUG 2025
IJmuiden Ver Beta permit amended into 2 × 1 GW phases (2029 / 2032) following Delta Rhine Corridor delays. Gamma added a second 1 GW lot.
DESIGNATED · MAR 2026
The revised North Sea Programme designates area 6/7 (indicatively up to 19 GW, about 11 GW in a first phase) and reshapes Doordewind to fit Doordewind II. Lagelander is dropped. This is space only: no plots, tender or landfall yet, and landfall routes are studied in pVAWOZ, due end of 2026.
METHODOLOGY
Go-live dates for NL projects under construction, planned or in tender are Birdview Energy estimates, not RVO commitments. They include expected slippage versus the official roadmap based on: tender failures (Nederwiek I-A, Oct 2025), TenneT HVDC platform delivery, the Delta Rhine Corridor schedule, and supply-chain capacity. Several tendered sites are modelled as multi-phase deliveries: IJmuiden Ver Beta (Phase 1 / Phase 2), and the IJmuiden Ver Gamma A+B 2026 tender. Operational NL projects and all non-NL projects use the publicly reported commissioning year. Look for the • BIRDVIEW EST. badge in project details.
03

Project register

27 projects
Project▲ Country▲ Type▲ Status▲ Year▲ Capacity (MW)▲ Turbines▲ Distance (km)▲